Sequenced remediation programme derived from the mitigation plan, with schedule and budget envelope.

Planning assumptions

CAPEX estimate

$241,500

OPEX estimate (annual)

$138,000

Total year one

$379,500

Timeline — 28 weeks over a 12-month horizon
Segment camera/NVR VLAN and block east-west RTSPW1–W7
Firmware campaign for weaponized ONVIF CVEW4–W14
Rotate default credentials on IoMT fleetW9–W12
Deploy OT-aware IPS at Plant North uplinkW11–W23
Forward OT syslog to SIEM with ICS parsersW17–W22
Quarantine policy automation via NACW20–W28
Work packages
PackageOwnerPriorityDurationCAPEXOPEX / yr

Segment camera/NVR VLAN and block east-west RTSP

MIT-01

Network Ops
P1
6 w$45,000$12,000

Firmware campaign for weaponized ONVIF CVE

MIT-02

Facilities IT
P1
10 w$0$38,000

Rotate default credentials on IoMT fleet

MIT-04

Biomed
P1
3 w$0$8,000

Deploy OT-aware IPS at Plant North uplink

MIT-03

Security Eng
P2
12 w$120,000$26,000

Forward OT syslog to SIEM with ICS parsers

MIT-05

SOC
P2
5 w$15,000$22,000

Quarantine policy automation via NAC

MIT-06

Network Ops
P3
8 w$30,000$14,000